iluvfreetools
Site & safety46 of 46

Risk assessments, method statements, SWMS and job hazard analyses, for the UK, US, Australia and Canada. Finished documents, no empty boxes left for you.

All 46 ›
Structure & materials35 of 35

Steel, timber, concrete, brickwork, boards, groundworks and roofs. Section data, indicative sizing, quantities and the reference tables you normally go hunting for.

All 35 ›
Home & property32 of 32

See what it would look like before you commit, then work out what it takes. Upload a photo of your own wall, drive or house and try things on it.

All 32 ›
Invoices & docs20 of 20

Invoices, quotes, receipts and the rest of the paperwork, generated properly. No account, no watermark, and Download is the only button.

All 20 ›
Money & tax39 of 39

Wages, mortgages, tax and the everyday sums. What you actually take home, what it actually costs, and what you actually owe.

All 39 ›
People & hours46 of 46

Rotas, rosters and schedules, holiday and PTO, timesheets and staff paperwork. The admin that eats a Sunday evening, done in ten minutes.

All 46 ›
Business & marketing50 of 50

Starting up, getting found and keeping the admin straight. Everything downloadable, nothing paywalled at the last step.

All 50 ›
PDF & documents27 of 27

Merge, split, crop, sign, number and compress. Everything runs in your browser, so the contract you open here never reaches a server.

All 27 ›
Image tools24 of 24

Convert, resize, compress, crop and adjust. All of it on your own machine, with no upload, no account and no watermark on anything.

All 24 ›
Text & dates20 of 20

Word counts, case, days between dates, working days and ages. The ten-second look-ups, with no account and nothing stored.

All 20 ›
Random & party27 of 27

Secret Santa, draws, brackets, sweepstakes, printables and party quantities. The bit that is just for fun, done properly.

All 27 ›
Training & tests21 of 21

Practice tests for the cards and licences that decide whether you can work. Every answer cites the guidance it came from, not a forum.

All 21 ›

Steel erection SWMS

Free. No account, no email, nothing uploaded.

Start from a trade Welding and steel erection Ticks the categories that usually apply and writes three rows to edit. It cannot know your site, your plant or your people, which is the half that decides whether the document is any good.

The one welding and steel erection forgets. Steel is stable when it is finished and not before. The temporary support limb covers work needing support to prevent collapse, and a frame part way through erection is exactly that: it stands on its temporary bracing and guys until the last connection is made. The limb gets read as being about existing buildings.

One activity per statement. A SWMS covering everything on the job covers nothing usefully, and a reviewer will say so.
Which high risk construction work is involved 4 of 18 A SWMS is required for these specifically. Tick everything that applies: most jobs involve more than one, and the missed one is usually powered mobile plant moving nearby.
  • Queensland uses 3 metres for housing construction and 2 metres for everything else. South Australia moved from 3 to 2 metres on 1 July 2026.

The work, step by step Every task needs the last column filled in. It is the one the regulation asks for by name and the one that separates a SWMS from a method statement with an Australian title.
1
Who checks, when, and what happens if it is wrong. "As required" is what gets a SWMS sent back.
2
Who checks, when, and what happens if it is wrong. "As required" is what gets a SWMS sent back.
3
Who checks, when, and what happens if it is wrong. "As required" is what gets a SWMS sent back.
Who and where
Consulting the workers doing the work is a duty in its own right, not a formality, and a statement written without it is usually obvious to whoever reviews it.
Where it stands 3 tasks
1

thing still needed before this is a complete SWMS.

HRCW
A risk of a person falling more than 2 metres
HRCW
Work in an area that may have a contaminated or flammable atmosphere
HRCW
Work in an area where powered mobile plant is moving
HRCW
Work in an area with artificial extremes of temperature
  • Every row here is still the example text. A SWMS has to describe the work you are actually doing, on this site, with your plant and your people, and a reviewer spots a generic one immediately. Edit the rows that nearly fit, delete the ones that do not, and add what is missing.

This produces the document. Whether it is adequate for your actual work, plant and site is the judgement of whoever prepares and signs it, and of the principal contractor who accepts it. Nothing here makes it compliant.

Built in your browser. Nothing is uploaded, no account, and the finished PDF carries your own branding rather than ours.

Worth doing

  • Nobody is recorded as consulted. Consultation with the workers doing the work is a duty in its own right, and a SWMS written without it is usually obvious to whoever reviews it.
  • Nobody is named as having prepared it.
  • No site or project named.
  • 3 tasks have nobody responsible named.

Worked out on this device, by this page. Nothing you typed was sent anywhere or stored, and closing the tab loses it.

Next in the same job

Pre-ticked for falls, atmosphere, plant and temperature, with three rows written. A steel frame is stable when it is finished, and every hour before that it is standing on its temporary bracing.

A part-erected frame is a temporary structure

The temporary support limb covers work needing support to prevent collapse, and it gets read as being about existing buildings and propping. A frame part way through erection is exactly what it describes: it stands on its temporary bracing and guys until the last connection is made, and the bracing is a designed part of the job rather than something added when it feels lively.

Which is why the sequence and the bracing are designed together, and why the crane is not released until the bracing for that stage is in. Two bolts minimum in each connection before the hook comes off is the working rule, and it exists because a member held by one bolt is a hinge.

Fume is decided by what is on the steel, not by the process

The coating matters more than the arc. Galvanised steel produces zinc oxide, primed and painted steel produces whatever the coating decomposes into, and stainless produces hexavalent chromium, which is a carcinogen. The same welder doing the same weld on bare steel is in a completely different exposure.

So the first control is removing the coating back from the weld area before striking an arc, which is elimination rather than management. Local exhaust ventilation at the arc comes next, and it has to move with the work: extraction left at the bench while the welder is six metres away is doing nothing at all.

The fire is usually an hour after the arc

Hot slag and spatter fall, lodge in something combustible and smoulder. The fire starts after the crew has moved on, which is why a fire watch that ends when the welding ends is the one that misses it. Sixty minutes after the last arc is the usual minimum and longer where the material below could not be cleared.

The other half is looking down before starting. Sparks travel a long way vertically, and the combustible material is often somebody else material: packaging, membrane, a stack of insulation delivered that morning to the floor below.

Getting to the connection without climbing the steel

Access by MEWP is the first option, and free climbing the frame is the practice this trade has been moving away from for good reason. Where an unprotected edge cannot be avoided, fall arrest goes to a designed anchor rather than to whatever looks solid, and the rescue plan is written before anybody clips on.

Perimeter netting and void covers go in as the frame goes up rather than as a later package, because the gap between the steel being up and the edge protection arriving is exactly when people are working on it.

Arc eye reaches people who are not welding

Photokeratitis is a burn to the surface of the eye from ultraviolet light, and it does not need you to look at the arc. A reflection off a light-coloured wall or a bright steel surface is enough, and the pain arrives six to twelve hours later, usually in the middle of the night.

Which is why screens go round the arc rather than in front of the welder. The person who ends up in an emergency department is often a labourer who walked past twice, and they will not connect it to the welding because nothing hurt at the time.

Common questions

Is structural steel erection always high risk construction work?

In practice yes, and usually through several categories at once: falls over 2 metres, powered mobile plant moving in the area, and temporary support to prevent collapse while the frame is incomplete. Site welding can add the contaminated atmosphere limb depending on the location and the coating.

Does site welding need its own statement?

It is a different activity from erection, with different hazards and often a different crew, so it usually earns its own. Where the welding is a small part of the erection sequence it can sit inside the erection statement, provided the fume, fire watch and access controls are written properly rather than mentioned.

What extraction is needed for welding fume?

Local exhaust ventilation positioned at the arc and moved with the work, with the coating removed back from the weld area first. General ventilation dilutes fume across the space rather than capturing it, so it protects everybody slightly and the welder least of all, which is the wrong way round.

How long should the fire watch continue?

At least sixty minutes after the last arc as a normal minimum, and longer where combustible material below could not be removed. The reason is that slag smoulders: the fire that results from hot works usually starts well after the noise has stopped and everybody has gone.

Can I use a UK method statement for Australian steel work?

Not as it stands. The content is a reasonable starting point, and a SWMS has to name which high risk construction work is involved and say how the control measures will be implemented, monitored and reviewed. A method statement has no column for that last part, so it will come back.